TyBOT
Project & Crew Information:
- General Contractor: Brayman Construction Corporation
- Rebar Contractor: N/A (Self-Perform)
- Union: IW Local 787
- Crew Size: 8-person
- Shift Duration: 10-hour
- Products Used: TyBOT & IronBOT
- September 2026
ACR Project Scope:
- 4-Span Bridge Deck
- Bridge Deck SF: 20,915
- Width:44.5’
- Length: 470’
- Total Deck Rebar: 162,390 LBS
- Required Tied Intersections: 39,181
- Tie Specs: 50% Bottom / 50% Top
TyBOT Performance Metrics:
- Actual Ties: 29,316 (75% Total)
- Active Production Hours: 28.29
- Active Tie Rate: 1,036 Ties/HR
- Total Equipment Hours: 46.23
- Active Production Rate = 61%
- Equipment Utilization Rate = 57%
IronBOT Performance Metrics:
- Actual Pounds Placed: 159,826 (98% Total)
- Active Production Hours: 39.5
- Active Placement Rate: 4,046 LB/HR
- Total Equipment Hours: 60.5
- Active Production Rate = 65%
- Equipment Utilization Rate = 64%